Dear Experts,
I have a requirement to connect 2 clients of same ECC i.e. Client 100 and 200 to Quality SAP PO so that Client 100 can be used as Training and Client 200 can be used for UAT in Quality Landscape.
I know this can be done by doing extra configurations in Integration Directory by repeating the same scenario for both the clients 100 and 200.But this leads to some confusion then how could be my CTS+ transport strategy.
Am I following the correct approach in SLD for ECC business system.
Query 1 :
Does below entries for SLD in quality SAP PI would work?
Source | Target |
DEV ECC 100 | QUALITY ECC 100 |
QUALITY ECC 200 |
Query 2 :
What extra precautions should I take in such scenario apart from the proxy config separately I do in ECC like Application system and presence of Quality Business System in Quality PI SLD
Query 3 :
After the transport of ID objects in Quality SAP PI , would it allow me to make changes and create configuration scenario separately for Client 100 and 200.
Regards
Rebecca