Hi
We are planning to do a phased migration of SAP PI 7.0 to 7.31. We decided to go with new installation of 7.31 so we can have less downtime during our migration process. We have 200+ interfaces out of which 160+ are either inbound or outbound from SAP ECC using IDOC/Proxy/JDBC/FTP/Rosettanet adapters. The following are my questions
- Is there a possibility of moving few interfaces at a time so we wont cause impact to our business operations or potential risk
- Can we run PI 7.0 and PI 7.3 for a period of time till we complete entire migration
- Can we move 10 outbound idoc interfaces out of 20 outbound idocs and use same approach for inbound idocs/proxy/JDBC etc.
I saw the blogs on this where they ask some modifications to be done for proxy interfaces so ECC can connect to multiple PI systems. Want to know anybody who did a successful migration similar to this.
Thanks in advance.
Thanks
Kannan